
Demolition of interior to the bare studs, including asbestos removal. |

Restoring the original arch construction of the entry way into the
hallway. |

Rebuilding the framing of the doorways leading to the meeting rooms. |
Restored arch belonging to the entryway leading to the room that housed
the original council chambers. Architectural design completed by Don
Switzer. |

Earthquake retro-fit tying the un-reinforced brick walls to the ceiling
with steel braces. |

Steel structure frames the building providing support to the building
foundation. |

Foyer ceiling restored to its
original design. Earthquake retro-fit reinforcement can be seen on
the edges. Prism Construction was the engineering firm performing
the work. |

Earthquake retro-fit of the
masonry arch leading to the hallway. |

The outside of the building had
to be restored to its original facade. |

The exterior of the building
being prepared for new coats of paint. |

Refinished south facade. |

Arch entrance was rebuilt and
the roof was donated by Brea roofing. |

Window restoration. Most of the original panes still remain and were
preserved. |

Refinished exterior. |

Lion Claude Bradley provides
instructions of framing to Lion Joe Rollino and volunteer Walt Tees. |

Volunteers discuss the process
for framing the original window sills. |

Volunteer cutting steel stud
material to size. |

Volunteers start the steel stud
installation process. |

Claude Bradley affixes the
studs to the masonry wall. Studs were donated by Western Steel. |

Original volunteer Walt Tees of Diamond Bar working with framing
materials. |

The framing of the storage
closet for tables and chairs. |

The framing of the original
windows. |

Full view of the main meeting
room where the installation of the steel beams is complete. |

The installation of the
electrical conduit. |

Installation of a sprinkler
system bringing the building up to code. |

The hunt for the sewer system
connection begins. |

Coring of the concrete in the
fire truck parking bay in preparation for bathroom plumbing. |

Initial installation of the
rough plumbing for the new bathrooms. |

Completed installation of the
main line. |

We found it. The sewer connection and we did it without the aid
of a GPS unit. |

Installation of the manifolds that the toilets will be connected to when
the drywall work is complete. |

The old electrical system, complete with temporary extension cords and
fuses. Are you young enough to know what a fuse is? |

The new electrical system developed to meet the latest code. |

Donation of drywall by U.S. Gypsum. |

The beginning of the installation of insulation and drywall. |

Drywall work in the original jail. The bars still remain on the
outside of the building safeguarding the window. |

The drywall in the basement,
which housed the extended jail. |

Additional drywall work in the
basement. |

The framing of the doors
leading to the bathrooms on the lower level of the building. |

Restoration of the original arches located in the hallway. |

The redevelopment of the arched ceiling in the entry foyer. |

Drywall work in what will be
the warming kitchen on the lower level of the building. |

Installation of some of the
HVAC components. |

Installation of custom door jambs necessitated by retro-fit work. |

Setting of new mahogany doors. |

Door hardware, which approximates the original hardware back in 1929. |

Three coats of Urethane to protect the doors. |
Installation of Cat 5 cable for a future voice/data network. |

Initial installation of the ceiling grids and panels in the meeting rooms. |

A view of the southwest meeting
room where the ceiling installation is complete. |

Installation of the specialized
wall board necessary for the tile installation. |

Installation of the tile
bathroom floor installed by Coyle Construction. |
Bathroom wall tile installation begins. Tile donated by Pawlack
Tile. |

Completed bathroom tile work. |

Decorative tile design
pattern for the bathrooms. |

Plumbing fixture installation
work begins. |

Toilet installation complete. |

Complete men's bathroom. |

Reconstruction of the floor in
the upstairs meeting room. |

Installation of tile floor in the warming kitchen. Tile donated by
Pawlack Tile. |

Installation of the tile floor
in the main hallway. |

Lions Claude Bradley and Tom
Anthony applying finish coats to the interior walls of the southwest
meeting room. |
Preparing the floor for the installation of carpet that was donated by
Magic Carpet. The view is the south east meeting room. |

Primer coat applied to the
walls of the upstairs meeting room. |

Lion Bill Higgins applying
specialized paint on the metal window panes. |

Carpeting installed on the
stairway leading up to the upstairs meeting room. |

Floor preparation of the main meeting room. The rough textured floor
was where the safe used by the City Treasurer. |

The view of the finished main meeting room. |

Refinishing of the original oak stairs leading to the lower level of the
building. The oak is an 13/4" thick. |

Installation of lights in what
will be the warming kitchen. |

One of the wives making sure
the volunteers stay focused and quietly wonders when the 12 year old
project will really be completed. |

Another stage in the
restoration of the ceiling in the entrance foyer. |

A look of the completed ceiling
of the entrance foyer. |

A view of the restored main
hallway facing out toward Brea Blvd. |

A view of the restored main hallway facing west from the main entrance of
the building. |

Restored stained glass piece
installed in the early 60's and crafted by a city employee. |

Refinished new entry doors
minus the glasswork. |

A view of the etched glass with the Girl Scout and Boy Scout insignia's. |
|
|
 |
The annual Brea
Lions Scoutcenter Auction is one of the ways we raise funds to help us complete and maintain
this historical jewel of the city. Lion's Dave and Julie La Neve are
the auctioneers pictured here. Lorena Kolb and Lion Dr. Mark
Piekarski, both Brea business people have also handled the auctioneer
duties. |
|
| |
|
|
|